Maxim overcomes dual lift challenge

Premium Content

04 February 2016

Maxim Crane Works used two Grove GMK6400s for this dual lift

Maxim Crane Works used two Grove GMK6400s for this dual lift

Bridgeville, Pennsylvania, USA-based Maxim Crane Works completed a challenging dual pick at an energy plant in Cincinnati, Ohio.

The company chose two 450 US ton (400 tonne) Grove GMK6400 wheeled mobile telescopic cranes for the delicate lift, which was a 75 US ton (68 tonne) vessel lift at the facility.

The biggest hurdle was manoeuvring the orientation of the vessel – it was situated north to south, but need to be placed through a roof hatch aligned east to west.

To facilitate the dual rigging, Maxim used a 100 ton (91 tonne) beam with a centre lug that acted as a swivel to rotate the vessel when placed over the roof hatch. The work took about a day.

Latest News
Crane Institute of America appoints L.D. Stutes as GM
Stutes enters this newly created position with 37 years of experience.
Navigating new immigration policies in the construction industry
Joel Dandrea discusses what construction contractors need to know.
Link-Belt veteran William “Skeeter” Collins announces retirement
Collins, a cornerstone of Link-Belt Cranes’ sales team for over 50 years, will retire in February 2025