Big Carl lifts the final ring at Hinkley Point + video

third and final ring lifted in using Big Carl on second reactor building How about that for a rigging job. Big Carl lowering the 423 tonne load into the reactor building. Photo: Hinkley Point C/EDF Energy

A 5,000 tonne capacity crane from Sarens was used to lift into place a 423 tonne steel ring at the UK’s Hinkley Point C nuclear power station construction project.

Lifted on 14 October by the SGC-250 super heavy lift ring crane known as Big Carl, it is the third and final steel liner element on the site’s second reactor building. The steel ring is 47 metres in diameter and 11.6 metres tall. It forms part of the inner containment wall and will be encased in two layers of concrete.

Building efficiency

giant rusty steel ring lifted by yellow and blue Sarens SGC-250 giant ring crane The Sarens SGC-250 has a capacity of 5,000 tonnes. Photo: Hinkley Point C/EDF Energy

As the top of the three rings this last one also includes mountings for the rotating polar crane to be installed on top. The polar crane is used when refuelling the reactor.

The steel dome over the building will be installed in 2025. This was done on the first reactor building in December 2023 and it is now ready for the reactor to be installed. Having learned from building the first reactor building, the second one has achieved efficiencies in its construction of between 20 and 30 per cent, according to an Hinkley Point C spokesperson.

Watch a video of the project.

Latest News
Fluor JV gets go-ahead to start work on US$45 billion Hanford nuclear site cleanup
US government awards 10 year clean up contract worth up to US$45 billion for Hanford former nuclear site
ML Crane and Winslow now under CSI name
The ML Crane Group and Winslow Crane have been consolidated as Crane Service Inc
CIC’s new scoring system speeds up certification process
Crane Institute Certification’s new computerized scoring tells an operator within hours whether he or she passed the OSHA-required practical exam.