In April ALE was tasked with lifting the 500 tonne arched centre section of the Vicaria Bridge in Albacete, Spain. The operation was carried out using an auxiliary steel structure comprising beams supported over each transverse girder of the lateral spans. Four 200 tonne capacity HLS200 strand jacks were installed on the auxiliary sections.

The lifting began by progressively taking of the load until the central span of the arch was detached from its temporary supports. Following a topography test, the arch section was levelled and the four units began their simultaneous 40 m lift.

When the central span was close to its final elevation, another topography test was carried out. The span was then lifted into its final position and connected to the outer bridge decks. The job was completed in one day.

Latest News
Link-Belt’s 65|RT delivers power and precision on transmission project
The rough terrain crane has been integral to setting rebar cages and anchor bolt cages into 17 drilled pier foundations.
Friday roundup: smarter and safer transport; China’s new towers; defying the slowdown; Tadano promises surprises
This week’s CTB covered making transport safer, Chinese tower cranes and the strong market in North America
AMHEC orders 100 Tadano RT cranes
Historic deal for 80 tonne capacity rough terrain cranes for oilfield work in Saudi Arabia