Last foundation pile for Westermeerwind

Premium Content

08 June 2015

Last foundation pile installed for Westermeerwind nearshore wind park

Last foundation pile installed for Westermeerwind nearshore wind park

Heavy lift and specialized transport service provider Mammoet has completed the installation of the foundation piles for the offshore Westermeerwind wind park in Ijsselmeer Lake, Netherlands.

The project is being carried out by a joint venture between Van Oord and Mammoet. In total, 48 foundation piles have been installed at the site, with on average one being installed per day.

Peter de Weijs, Westermeerwind project director, said, “We are very satisfied with how well the installation of the foundation piles went. Despite the fact that we were dependent on the weather, everything proceeded extremely smoothly. The construction of the Westermeerwind wind park is right on schedule.”

The laying of 44 km of power cables between the foundations and the transformer station is now underway. The installation of the 48 wind turbines will begin in mid-July. The 3 MW turbines will be installed in two rows along the Westermeerdijk and one row along the Noordermeerdijk. The park is scheduled to be completed in February 2016 and is expected to produce wind energy for 160,000 households, a spokesperson said.

Siemens is the head contractor for the Westermeerwind wind park project and will maintain the site for at least fifteen years. Subcontractors include Van Oord and Mammoet for the foundations and the installation of the wind turbines, and VolkerWessels Boskalis Marine Solutions (VBMS) for the cabling to the transformer station.

Truckstop.com and ProMiles partner up to streamline heavy haul quoting
Truckstop.com and ProMiles have expanded the Heavy Haul Load Board with route-based quoting for oversize and overweight freight.
SCRA issues statement on tariff ruling by Supreme Court
Industry association comments on US ruling overturning import tariffs
Mi-Jack acquires new facility in Illinois, USA
New 200,000 square-foot production facility to meet critical capacity needs