Three Mammoet ring cranes, one job

12 September 2017

Three of Mammoet’s biggest ring cranes are being used at the same time on one job site to help realise an ambitious construction schedule for Malaysian oil and gas multinational Petronas. Mammoet said that never before have three ring cranes of this size been used on one job site at the same time.

Mammoet

The Pengerang Integrated Complex (PIC) job site

The three Mammoet ring cranes being used are: the PT 50; the PTC 35; and the PTC 140. According to Mammoet, its ring track cranes combine a wide reach and high capacity on a small footprint with the ability to turn 360 degrees. Together the three cranes have a capacity of 10,000 tons and 225,000 ton metres.

 

The cranes are being used to construct the Pengerang Integrated Complex (PIC) which, when finished, will comprise oil refineries, naphtha crackers, petrochemical plants, liquefied natural gas (LNG) import terminals, and a regasification plant.

Mammoet has had a presence on the job site since 2016 and at some points up to 35 Mammoet cranes have been working there, the company said.

Latest News
Vernazza Autogru uses Tadano crawler cranes to lift Genoa shipyard bridge
Italian heavy lift specialist Vernazza Autogru used two Tadano lattice boom crawler cranes to install a prefabricated steel and concrete bridge at the entrance to Genoa’s Prà shipyard, crossing a major motorway and railway line. Lucy Barnard finds out how
Select Crane names appoints Mid-Atlantic territory manager
Bruce Alvis brings with him more than 25 years of expertise in the crane and industrial equipment sector. 
Green energy projects drive rise in UK infrastructure approvals
Go-ahead for US$4.5 billion offshore floating wind farm helps bolster latest figures